Nova Patents
EP1516849A2

Crane

Abstract

The crane has an upper structure (4) rotatable around a vertical axis (3), a jib (5) connected to luff around a horizontal axis (6), a luffing device (8-10) for the luffing up and down of the jib, and an operating ballast (7) to counteract the moment of the jib. An erection sub-frame (11) is fastened on the upper structure and/or on the operating ballast, projecting rearwards, and is connected to an erection ballast (16) to assist in the erecting of the jib. The erection sub-frame has means of connection (14) for the attachment of a mobile crane as ballast.

EP1516849A2, drawing sheet 1
Sheet 1 of 2

Term

Term ended

Projected expiry passed 2 September 2024, 2.1 years ago.

  1. Priority
  2. Filed
  3. Published
  4. Projected expiry
  5. Today

10 claims: 10 independent, 0 dependent

  1. 1
    Crane with a rotatable about an upright axis (3) superstructure (4), a the superstructure (4) about a horizontal axis (6) luffing articulated boom (5), a tilting mechanism (8, 9, 10) for luffing up and down of the boom (5) and a the moment of the jib (5) counteracting operating ballast (7) characterized in that an auxiliary erecting frame (11) is provided on the upper carriage (4) and / or the operating ballast (7) rearward cantilever fastened and with an erecting (16) is connectable for erecting the jib (5). Kran mit einem um eine aufrechte Achse (3) drehbaren Oberwagen (4), einem am Oberwagen (4) um eine horizontale Achse (6) wippbar angelenkten Ausleger (5), einer Wippvorrichtung (8, 9, 10) zum Auf- und Abwippen des Auslegers (5) sowie einem dem Moment des Auslegers (5) entgegenwirkenden Betriebsballast (7), dadurch gekennzeichnet, dass ein Aufrichtehilfsrahmen (11) vorgesehen ist, der an dem Oberwagen (4) und/oder dem Betriebsballast (7) nach hinten auskragend befestigbar und mit einem Aufrichtehilfsballast (16) für das Aufrichten des Auslegers (5) verbindbar ist.
  2. 2
    Crane according to the preceding claim, wherein the auxiliary erecting (11) suspension means (14) for attaching a mobile auxiliary crane as erecting (16). Kran nach dem vorhergehenden Anspruch, wobei der Aufrichtehilfsrahmen (11) Anhängemittel (14) zum Anhängen eines mobilen Hilfskrans als Aufrichtehilfsballast (16) aufweist.
  3. 3
    Crane according to one of the preceding claims, wherein the suspension means (2) in the longitudinal direction of the auxiliary erecting frame (11) spaced apart Fastening elements (14), whose distance from each other, adjustable is. Kran nach einem der vorhergehenden Ansprüche, wobei die Anhängemittel (2) in Längsrichtung des Aufrichtehilfsrahmens (11) voneinander beabstandete Befestigungselemente (14) aufweisen, deren Abstand voneinander einstellbar ist.
  4. 4
    Crane according to one of the preceding claims, wherein the fastening elements (14) are borne by crossmembers (12), of which at least a longitudinal direction of the auxiliary erecting frame (11) positionally variable, preferably is slidably disposed. Kran nach einem der vorhergehenden Ansprüche, wobei die Befestigungselemente (14) von Querträgern (12) getragen werden, von denen zumindest einer in Längsrichtung des Aufrichtehilfsrahmens (11) lageveränderbar, vorzugsweise verschieblich angeordnet ist.
  5. 5
    Crane according to one of the preceding claims, wherein the suspension means (14) of the auxiliary erecting frame (11) has a height adjuster (13), preferably each one fixing element (14) associated threaded spindles (13). Kran nach einem der vorhergehenden Ansprüche, wobei die Anhängemittel (14) des Aufrichtehilfsrahmens (11) eine Höheneinstellvorrichtung (13), vorzugsweise einem jeden Befestigungselement (14) zugeordnete Gewindespindeln (13), aufweisen.
  6. 6
    Crane according to one of the preceding claims, wherein the auxiliary erecting (11) for operating the crane from its projecting rearward erection position in a crane operating position can be brought, in the erecting (11) preferably substantially within a superstructure from (4) defined pivot range. Kran nach einem der vorhergehenden Ansprüche, wobei der Aufrichtehilfsrahmen (11) für den Kranbetrieb aus seiner nach hinten auskragenden Aufrichtestellung in eine Kranbetriebsstellung bringbar ist, in der der Aufrichtehilfsrahmen (11) vorzugsweise im wesentlichen innerhalb eines vom Oberwagen (4) definierten Schwenkbereichs liegt.
  7. 7
    Crane according to one of the preceding claims, wherein the auxiliary erecting (11) pivotable, preferably about a substantially horizontal Axis, the superstructure (4) and / or operating ballast (7) is articulated and through a pivoting device (17), preferably at least one hydraulic Linkage between its projecting rearward erection position and a preferably upwardly pivoted operating position pivoted is. Kran nach einem der vorhergehenden Ansprüche, wobei der Aufrichtehilfsrahmen (11) schwenkbar, vorzugsweise um eine im wesentlichen horizontale Achse, am Oberwagen (4) und/oder Betriebsballast (7) angelenkt und durch eine Schwenkvorrichtung (17), vorzugsweise zumindest einem hydraulischen Kraftheber, zwischen seiner nach hinten auskragenden Aufrichtestellung und einer vorzugsweise nach oben geschwenkten Betriebsstellung verschwenkbar ist.
  8. 8
    Crane according to one of the preceding claims, wherein the auxiliary erecting (11) with releasable fastening means releasably secured collapsible, is bolted in particular by fixing bolts on the upper carriage (4). Kran nach einem der vorhergehenden Ansprüche, wobei der Aufrichtehilfsrahmen (11) mit lösbaren Befestigungsmitteln lösbar befestigt und demontierbar, insbesondere mittels Befestigungsbolzen am Oberwagen (4) verbolzt ist.
  9. 9
    Crane according to one of the preceding claims, wherein the auxiliary erecting (11) is mounted free of bracing on the superstructure (4). Kran nach einem der vorhergehenden Ansprüche, wobei der Aufrichtehilfsrahmen (11) frei von Abspannungen am Oberwagen (4) befestigt ist.
  10. 10
    Crane according to one of the preceding claims, wherein the auxiliary erecting (11) about the operating ballast (7) rearwardly projecting cantilevered length has at least the distance of the operating ballast center of gravity of the superstructure axis of rotation (3). Kran nach einem der vorhergehenden Ansprüche, wobei der Aufrichtehilfsrahmen (11) eine über den Betriebsballast (7) nach hinten auskragende Kraglänge besitzt, die zumindest dem Abstand des Betriebsballastschwerpunkts von der Oberwagendrehachse (3) entspricht.