Installation of decks on offshore substructures

Abstract

A technique for the installation of a deck on an offshore substructure is particularly useful with a floating substructure. Two independent pontoons (10) each have two columns (14) spaced apart from each other that extend upwardly from the pontoon (10). On each pontoon (10), a support beam (16) attached to the columns (14) spans the space between the columns. Each pontoon (10) is provided with ballast tanks (18,20) that allow the pontoons to be selectively ballasted or de-ballasted to control pontoon depth for receiving a deck or installing a deck on the offshore substructure. The pontoons (10) may be ballasted down during transit of the deck such that the main body portion of the pontoons is below significant wave action and the columns (14) present a relatively small water plane area. The pontoons (10) allow the deck to be placed directly above the offshore substructure. For a floating substructure, the pontoons (10) are ballasted while the floating substructure is simultaneously de-ballasted to transfer the deck to the floating substructure.

EP0911255A2, drawing sheet 1
Sheet 1 of 8

Term

Term ended

Projected expiry passed 12 October 2018, 8 years ago.

  1. Priority
  2. Filed
  3. Published
  4. Projected expiry
  5. Today

4 claims: 3 independent, 1 dependent

  1. 1
    A method for the installation of a deck on a floating offshore substructure, comprising:a. placing the deck on a floating barge such that the deck extends beyond the edges of the barge;b. providing at least two buoyant pontoons each formed from a main hull portion having two columns spaced apart from each other along the length of the hull and extending upwardly therefrom and a support beam between said columns;c. ballasting said pontoons such that the support beams thereon are below the lower portion of the deck;d. positioning said pontoons on either side of the barge such that said pontoons are under the deck;e. de-ballasting said pontoons such that said pontoons support the deck independently of the barge;f. positioning said pontoons to straddle the floating offshore substructure such that the deck is above the top of the floating offshore substructure;and g. ballasting said pontoons and de-ballasting the floating offshore substructure to transfer the deck to the floating offshore substructure.
  2. 2
    A method for the installation of a deck on an offshore substructure, comprising:a. placing the deck on a floating barge such that the deck extends beyond the edges of the barge;b. providing at least two buoyant pontoons each formed from a main hull portion having two columns spaced apart from each other along the length of the hull and extending upwardly therefrom and a support beam between said columns;c. ballasting said pontoons such that the support beams thereon are below the lower portion of the deck;d. positioning said pontoons on either side of the barge such that said pontoons are under the deck;e. de-ballasting said pontoons such that said pontoons support the deck independently of the barge;f. positioning said pontoons to straddle the floating offshore substructure such that the deck is above the top of the floating offshore substructure;and g. ballasting said pontoons to transfer the deck to the floating offshore substructure.
  3. 3
    A pontoon for use in installing a deck on an offshore substructure, comprising:a. a buoyant main hull portion having a plurality of ballast compartments;b. at least two columns spaced apart from each other along the length of said main hull portion and extending upwardly therefrom, said columns each having a ballast tank therein;and c. a support beam which spans the space between said columns.